How do I replace one provisional allowance with a selected finish and show the revised contract sum?
Remove the full included allowance once. The agreed uplift applies to the new finish only.
Open Allowance replacementTry the worked example
These are the example inputs from Allowance replacement. Replace them in the tool to run your own case.
| Original proposal (€) | Included allowance (€) | Selected net cost (€) | Agreed uplift (%) |
|---|---|---|---|
| 8400 | 1100 | 1240 | 12 |
Example result
Revised proposal · €8,688.80