How do I check whether approval and purchase lead times fit the remaining supplier-price hold?

Steps run consecutively on the same calendar. A negative hold margin means the quote may expire before order.

Open Quote validity buffer

Try the worked example

These are the example inputs from Quote validity buffer. Replace them in the tool to run your own case.

Days left on price hold (days)Technical review (days)Commercial approval (days)Order processing (days)Contingency (days)
216543

Example result
Hold margin · 3 days