How do I separate approved additions from pending requests and show the remaining client budget?
Approved omissions reduce commitment. Pending additions belong only in the what-if figure.
Open Scope freeze ledgerTry the worked example
These are the example inputs from Scope freeze ledger. Replace them in the tool to run your own case.
| Signed base scope (€) | Approved additions (€) | Approved omissions (€) | Pending additions (€) | Client ceiling (€) |
|---|---|---|---|---|
| 12800 | 850 | 450 | 760 | 14500 |
Example result
Committed value · €13,200.00
Who uses this?
Refurbishment coordinator. The free online tool runs the calculation in your browser. To edit the files and use the tools offline in one business, see the €49 offline edition.
Where the idea came from
A foreman’s site note becomes a job-specific handover that someone checks. This independent application adapts that idea to separate approved additions from pending requests and show the remaining client budget.